Third Party Monitoring Verification of Solar Home System, Household Biogas System, MSME and Solar Home System-Religious Package (RFP No: AEPC/NRREP/MQM/RFP/2075/76-03), Package-1
Location | Client/Finance | Period | Value of service | Remark |
---|---|---|---|---|
Illam, Jhapa,Morang, Sunsari | AEPC | April 2019 - July 2019 | NRs 0.94 Million | SITARA |
Post Evaluation of Six Hydropower Projects
1.) Chilime Hydropower Project,
2.) Khimti-1 Hydroelectric Project,
3.) Kali Gandaki A Hydropower Project,
4.) Modi Khola Hydroelectric Project,
5.) Lower Modi-1 Hydroelectric Project
6.)Middle Marsyangdi Hydropower Project
Location | Client/Finance | Period | Value of service | Remark |
---|---|---|---|---|
Rasuwa, Dolakha, Syangjha, Parbat and Lamjung | DoED | May 2015 - February 2017 | NRs 4.44 Million | SITARA-INSIGHT-SILT JV |
Third party monitoring verification of installed renewable energy system
Location | Client/Finance | Period | Value of service | Remark |
---|---|---|---|---|
Different District | NRREP/AEPC | February 2015 - August 2015 | NRs 1.7 Million | PIONEER SITARA JV |
Detailed Feasibility Study
Location | Client/Finance | Period | Value of service | Remark |
---|---|---|---|---|
Surkhet | BNA | September 2012 - March 2013 | NRs 0.1 Million | SITARA |
Preparation of Strategic Plan for the Development of Micro Hydro through DoLIDAR
Location | Client/Finance | Period | Value of service | Remark |
---|---|---|---|---|
Kathmandu | DoLIDAR | May 2012 - June 2012 | NRs 0.28 Million | SITARA |
Compilation of Mapping of Micro Hydropower and District Electrification Master Plan (MMHP & DEMP) Report and Upgrading in GIS of 53 Districts of Nepal.
Location | Client/Finance | Period | Value of service | Remark |
---|---|---|---|---|
53 Districts of Nepal | AEPC | May 2012 - July 2012 | NRs 0.508 Million | SITARA |
Detailed Engineering Survey, Design and Report Preparation of sukhadhik Khola MHP
Location | Client/Finance | Period | Value of service | Remark |
---|---|---|---|---|
Mugu | DDC Mugu | March 2012 - August 2012 | NRs 0.3 Million | SITARA |
Study on Technical Standards for Grid Connection of Micro Hydro in Nepal.
Location | Client/Finance | Period | Value of service | Remark |
---|---|---|---|---|
Nepal | AEPC | February 2012 - July 2012 | NRs 0.285 Million | SITARA |
Detailed Feasibility Study of Micro hydropower Projects
Location | Client/Finance | Period | Value of service | Remark |
---|---|---|---|---|
Palpa | REDA | January 2012 - September 2012 | NRs 0.15 Million | SITARA |
Conduct the Capacity Building of Stakeholders on Mini/Micro Hydropower Development in the Special District (Bajura & Achham)
Location | Client/Finance | Period | Value of service | Remark |
---|---|---|---|---|
Bajura & Achham | AEPC | May 2011 - June 2011 | NRs 0.89 Million | SITARA JV Peace |
Mapping of Micro Hydropower (MMHP) and Preparation of District Electrification Master Plan (DEMP) in Achham,Bajura, Doti,Dadeldhura, Gulmi,Arghakhachi, Syangja & Palpa Districts.
Location | Client/Finance | Period | Value of service | Remark |
---|---|---|---|---|
Achham,Bajura, Doti,Dadeldhura, Gulmi,Arghakhachi, Syangja & Palpa Districts | AEPC/MOEn | April 2011 - July 2011 | NRs 1.8 Million | SITARA |
Mapping of Micro Hydropower (MMHP) and Preparation of District Electrification Master Plan (DEMP) in Kavre, Sindhupalchowk, Dolakha, lalitpur, Khotang,Dhankuta & Terathum Districts
Location | Client/Finance | Period | Value of service | Remark |
---|---|---|---|---|
Kavre, Sindhupalchowk, Dolakha, lalitpur, Khotang,Dhankuta & Terathum Districts | AEPC/MOEn | April 2011 - July 2011 | NRs 1.75 Million | SITARA |
Preparation of Implementation Guideline and Technical Manual for Implementation of Micro Hydro Schemes.
Location | Client/Finance | Period | Value of service | Remark |
---|---|---|---|---|
Lalitpur | DoLIDAR/MoLD | May 2010 - August 2010 | NRs 0.5 Million | SITARA |
Detail survey , design and Preparation of Detailed Project Report (DPR) of Simrutu Khola Mini Hydro Project (200 kW) ,Rukum
Location | Client/Finance | Period | Value of service | Remark |
---|---|---|---|---|
Rukum District | MOST/AEPC/ESAP | November 2009 - June 2010 | NRs 0.65 Million | SITARA JV E2 |
Detail survey , design and Preparation of Detailed Project Report (DPR) of Upper Deumai Khola Small Hydro Project (12.8 MW)
Location | Client/Finance | Period | Value of service | Remark |
---|---|---|---|---|
IIam District | Progress Power Company | June 2008 - May 2010 | NRs 1.55 Million | SITARA |
Feasibility Study of 8 micro Hydro Power Projects
Location | Client/Finance | Period | Value of service | Remark |
---|---|---|---|---|
Illam | NCDC | May 2008 - May 2010 | NRs 0.4 Million | SITARA |
Detail survey, design , Cost estimate and Preparation of Tender document of Transmission and distribution of Haluwa Khola Mini Hydro Project (400KW), Five VDCS of Ramechhap.
Location | Client/Finance | Period | Value of service | Remark |
---|---|---|---|---|
Ramechhap District. | UNDP/REDP/KIND Project | January 2008 - July 2008 | NRs 0.35 Million | SITARA |